Congonhas reparará pista principal

AW | 2020 07 21 17:00 | AIRLINES / AIR TRAFFIC / AIRPORTS

Aeropuerto Congonhas cerrará pista principal a partir de Agosto 2020

La pista principal del Aeropuerto de São Paulo/Congonhas, se someterá a obras para recuperar el pavimento de asfalto. Con una inversión de R$ 11,5 millones, la intervención requerirá el cierre total de la pista durante 32 días. Durante el período, el aeropuerto operará a través de la pista auxiliar. Las obras comenzarán el 05/08, y su finalización está programada para el 05/09 de 2020. Para la ejecución de los servicios dentro del plazo establecido, se asignarán equipos las 24 horas del día, empleando mano de obra durante todos los días de la semana. La tecnología proporcionará, entre otros beneficios, una mejora en la capacidad de drenaje de la pista (drenaje rápido del agua de lluvia), con un aumento en la adherencia de los neumáticos de la aeronave al pavimento y una reducción en la posibilidad de aquaplaning (hidroplaneo). Las obras incluyen servicios de fresado para el revestimiento de asfalto existente, ejecución de una capa de hormigón de asfalto estructural (CBUQ) con ranurado en la región del promontorio; y capa de superficie de fricción porosa (CPA).

“Infraero está aprovechando la caída en el movimiento y las operaciones de pasajeros, debido a la pandemia de Covid-19, para avanzar en el cronograma de construcción de la compañía. En el caso de Congonhas, el trabajo es parte del mantenimiento periódico y servirá para garantizar que el aeropuerto continúe operando en condiciones normales, especialmente por seguridad, durante los próximos 10 años”, explica el Superintendente de Aeropuerto Congonhas, João Marcio Jordão.

Todas las acciones de planificación para el trabajo y para mantener la seguridad de las operaciones se alinearon y desarrollaron con la contribución de las aerolíneas, la Asociación Brasileña de Aerolíneas (ABEAR), la Asociación Brasileña de Aviación General (ABAG) y otras partes interesadas, como el Departamento de Control del espacio aéreo (DECEA), vinculado al Comando de la Fuerza Aérea, la Secretaría de Aviación Civil, el Ministerio de Infraestructura y la Agencia Nacional de Aviación Civil.

Pista Auxiliar

La Pista Auxiliar solo puede recibir aeronaves hasta la categoría 3C, como el ATR-72 y el Cessna Caravan, de acuerdo con las condiciones establecidas por la Agencia Nacional de Aviación Civil (ANAC) en conjunto con el aeropuerto, las aerolíneas y DECEA, cuyo objetivo es mantener la seguridad de operaciones durante el período de ejecución de las obras en la pista principal.

Azul continúa en Congonhas

Azul operará 17 vuelos diarios en Congonhas durante los trabajos en la pista. Con el cierre de la pista principal en el aeropuerto de Congonhas , para trabajos de restauración en el pavimento de asfalto, Azul hará ajustes a su red entre el 5 de agosto y el 5 de septiembre. La compañía mantendrá sus operaciones en la pista auxiliar del aeropuerto con aviones modelo ATR 72-600, que pueden transportar hasta 70 pasajeros, y ampliará la oferta de vuelos diarios a Bahía y en el puente Río-São Paulo, además de crear una nueva ruta Congonhas-Curitiba. Congonhas-Santos Dumont, que hoy tiene dos vuelos diarios, pasará a siete frecuencias diarias, mientras que el mercado Congonhas-Belo Horizonte tendrá seis operaciones por día en comparación con los dos que se han llevado a cabo. La ruta Congonhas-Curitiba, que ya fue operada por Azul el año pasado, tendrá nuevamente la oferta de asientos de la compañía, con cuatro conexiones diarias.

“En una planificación integrada con Infraero y otras autoridades aeronáuticas, reorganizamos nuestra red y estamos aumentando la oferta de asientos de Congonhas. Gracias a nuestra flota mixta, tenemos la flexibilidad de planificar la red y adaptarnos a diferentes escenarios operativos, manteniendo los altos estándares de seguridad de Azul. Con esta red ajustada entre agosto y septiembre, mantendremos la asistencia a los clientes en la ciudad más grande del país y también ampliaremos las posibilidades de conexión”, dice Vitor Silva, Gerente de Planificación de Redes de Azul Airlines.

Congonhas to repair main runway

Congonhas Airport will close the main runway during August 2020

The main runway of the São Paulo/Congonhas Airport will undergo works to recover the asphalt pavement. With an investment of R$ 11.5 million, the intervention will require the total closure of the runway for 32 days. During the period, the airport will operate through the auxiliary runway. The works will begin on 08/05, and its completion is scheduled for 09/05 2020. For the execution of the services within the established period, teams will be assigned 24 hours a day, using labor during all the days of week. The technology will provide, among other benefits, an improvement in the drainage capacity of the runway (rapid drainage of rainwater), with an increase in the adherence of aircraft tires to the pavement and a reduction in the possibility of aquaplaning ( hydroplaning). The works include milling services for the existing asphalt coating, execution of a structural asphalt concrete layer (CBUQ) with grooving in the promontory region; and porous friction surface layer (CPA).

“Infraero is taking advantage of the drop in passenger movement and operations, due to the Covid-19 pandemic, to advance the company’s construction schedule. In the case of Congonhas, the work is part of the periodic maintenance and will serve to guarantee that the airport continues to operate under normal conditions, especially for security, for the next 10 years”, explains the Congonhas Airport Superintendent, João Marcio Jordão.

All actions to plan for work and to maintain the safety of operations were aligned and developed with the contribution of airlines, the Brazilian Association of Airlines (ABEAR), the Brazilian Association of General Aviation (ABAG) and other interested parties, such as the Department of Airspace Control (DECEA), linked to the Air Force Command, the Ministry of Civil Aviation, the Ministry of Infrastructure and the National Civil Aviation Agency.

Auxiliary runway

The Auxiliary Runway can only receive aircraft up to category 3C, such as the ATR-72 and the Cessna Caravan, in accordance with the conditions established by the National Civil Aviation Agency (ANAC) in conjunction with the airport, airlines and DECEA, whose objective is to maintain the safety of operations during the period of execution of the works on the main runway.

Azul continues in Congonhas

Azul will operate 17 daily flights in Congonhas during work on the runway. With the closure of the main runway at Congonhas airport, for restoration work on the asphalt pavement, Azul will make adjustments to its network between August 5 and September 5. The company will maintain its operations on the airport’s auxiliary runway with ATR 72-600 model aircraft, which can carry up to 70 passengers, and will expand the offer of daily flights to Bahia and the Rio-São Paulo bridge, in addition to creating a new route. Congonhas-Curitiba. Congonhas-Santos Dumont, which today has two daily flights, will switch to seven daily frequencies, while the Congonhas-Belo Horizonte market will have six operations per day compared to the two that have been carried out. The Congonhas-Curitiba route, which was already operated by Azul last year, will once again have the company’s offer of seats, with four daily connections.

“In an integrated planning with Infraero and other aeronautical authorities, we reorganized our network and we are increasing the offer of Congonhas seats. Thanks to our mixed fleet, we have the flexibility to plan the network and adapt to different operating scenarios, maintaining Azul’s high security standards. With this network adjusted between August and September, we will continue assisting customers in the country’s largest city and we will also expand connection possibilities”, says Vitor Silva, Network Planning Manager at Azul Airlines.

Congonhas conserta pista principal

Aeroporto Congonhas fechará pista principal em Agosto 2020

A pista principal do Aeroporto São Paulo/Congonhas passará por obras de recuperação do asfalto. Com um investimento de R$ 11,5 milhões, a intervenção exigirá o fechamento total da pista por 32 dias. Durante o período, o aeroporto operará através da pista auxiliar. As obras terão início em 08/05 e a conclusão está prevista para 09/05 2020. Para a execução dos serviços dentro do prazo estabelecido, as equipes serão designadas 24 horas por dia, empregando mão de obra durante todos os dias de a semana. A tecnologia proporcionará, entre outros benefícios, uma melhoria na capacidade de drenagem da pista (drenagem rápida da água da chuva), com um aumento na aderência dos pneus de aeronaves ao pavimento e uma redução na possibilidade de aquaplanagem ( hidroavião). As obras incluem serviços de fresagem do revestimento asfáltico existente, execução de uma camada estrutural de concreto asfáltico (CBUQ) com canal na região promontória; e camada superficial por atrito poroso (CPA).

“A Infraero está aproveitando a queda no movimento e nas operações de passageiros, devido à pandemia do Covid-19, para avançar no cronograma de construção da empresa. No caso de Congonhas, o trabalho faz parte da manutenção periódica e servirá para garantir que o aeroporto continue operando em condições normais, principalmente por segurança, pelos próximos 10 anos”, explica o superintendente do aeroporto de Congonhas, João Marcio Jordão.

Todas as ações de planejamento do trabalho e manutenção da segurança das operações foram alinhadas e desenvolvidas com a contribuição de companhias aéreas, da Associação Brasileira de Companhias Aéreas (ABEAR), da Associação Brasileira de Aviação Geral (ABAG) e de outras partes interessadas, como o Departamento de Controle do Espaço Aéreo (DECEA), vinculado ao Comando da Força Aérea, à Secretaria de Aviação Civil, ao Ministério de Infra-estrutura e à Agência Nacional de Aviação Civil.

Trilha Auxiliar

A pista auxiliar só pode receber aeronaves da categoria 3C, como ATR-72 e Caravana Cessna, de acordo com as condições estabelecidas pela Agência Nacional de Aviação Civil (ANAC) em conjunto com o aeroporto, as companhias aéreas e o DECEA, cuja O objetivo é manter a segurança das operações durante o período de execução das obras na pista principal.

Azul continua em Congonhas

A Azul operará 17 vôos diários em Congonhas durante o trabalho na pista. Com o fechamento da pista principal no aeroporto de Congonhas, para obras de restauração no asfalto, a Azul fará ajustes em sua rede entre 5 de agosto e 5 de setembro. A empresa manterá suas operações na pista auxiliar do aeroporto com aeronave modelo ATR 72-600, que pode transportar até 70 passageiros, e expandirá a oferta de voos diários para a Bahia e a ponte Rio-São Paulo, além de criar uma nova rota. Congonhas-Curitiba. Congonhas-Santos Dumont, que hoje possui dois vôos diários, passará para sete frequências diárias, enquanto o mercado de Congonhas-Belo Horizonte terá seis operações por dia em comparação às duas que foram realizadas. A rota Congonhas-Curitiba, que já era operada pela Azul no ano passado, terá novamente a oferta de assentos da empresa, com quatro ligações diárias.

“Em um planejamento integrado com a Infraero e outras autoridades aeronáuticas, reorganizamos nossa rede e estamos aumentando a oferta de assentos em Congonhas. Graças à nossa frota mista, temos a flexibilidade de planejar a rede e adaptar-se a diferentes cenários operacionais, mantendo os altos padrões de segurança da Azul. Com essa rede ajustada entre agosto e setembro, continuaremos ajudando os clientes na maior cidade do país e também expandiremos as possibilidades de conexão”, diz Vitor Silva, gerente de planejamento de rede da Azul Airlines.

Ξ A I R G W A Y S Ξ
PUBLISHER: Airgways.com
DBk: Infraero.gov.br / Aeroportocongonhas.net / Airgways.com
AW-POST: 202007211700AR

A\W   A I R G W A Y S ®

Responder

Introduce tus datos o haz clic en un icono para iniciar sesión:

Logo de WordPress.com

Estás comentando usando tu cuenta de WordPress.com. Cerrar sesión /  Cambiar )

Google photo

Estás comentando usando tu cuenta de Google. Cerrar sesión /  Cambiar )

Imagen de Twitter

Estás comentando usando tu cuenta de Twitter. Cerrar sesión /  Cambiar )

Foto de Facebook

Estás comentando usando tu cuenta de Facebook. Cerrar sesión /  Cambiar )

Conectando a %s